- OBJECTIVE
To lay down the procedure for preventive maintenance of water treatment plant.
- SCOPE
This SOP is applicable for preventive maintenance of water treatment plant.
- RESPONSIBILITY
Water system operators/ Engineers | : | To follow the procedure |
- ACCOUNTABILITY
Head Engineering : System Compliance
- PROCEDURE:
- STARTING PROCEDURE:
- Engineering/Technician/Designee shall take approval prior to perform thePreventive
Maintenance activity of scheduled equipment from Concerned Department Head.
- As
perPreventive Maintenance schedule
take the machine under maintenance and put the “Under Maintenance” of
“Preventive Maintenance” board on the machine.
- Ensure the main power supply of system shall be switch OFF. If switch ON, then switch OFF the main power supply.
- Procedure/Checkpoints during Preventive Maintenance:
- Check all the electrical connections and tighten the same if required.
- Check the compressed air pressure at pressure gauge and ensure that it should be NLT 4 Kg/cm2 without any leakage.
- Clean the panel with the help of blower or compressed air.
- Check all pneumatic valves for proper functioning.
- Check the motor terminal connections of all the pumps and tighten the same.
- Check all the level sensors of the tank for their proper installation.
- Check all the dosing and regeneration tanks for proper cleaning and clean if required.
- Check the resin level (above middle level) in softener and top up if required.
- Switch ON the main power supply of the machine and check the supply voltage 415±5V with the help of Multimater/clamp meter.
- Check the current drawn by all the pump motors with the help of clamp meter.
- Check all the dosing pumps for proper functioning.
- Preventive Maintenance shall be done and same shall be recorded.
- After completion of Preventive Maintenance ensure the area around the system should be cleaned properly and record the Preventive Maintenance activity in respective Equipment Log Book.
- Remove the “Preventive Maintenance” or “Under Maintenance” Board from the system.
- Take the trial of the water system for proper functioning and after ensuring the proper operation of system, hand over the system for routine use.
- Frequency:
- Monthly
- Half Yearly.
TRAINING
Trainer : Head – Quality Assurance& Engineering Department.
Trainees : Engineering- Executive & Supervisors.
DISTRIBUTION
Master Copy : Quality Assurance Department
Controlled Copy : Engineering Department
Display Copy : Engineering Department (If Required)
8.0 ATTACHMENTS
Sr. No. | Annexure No. | Title | Format No. |
1 | NA | NA | NA |
- REFERENCES
In-house
10.0 ABBREVIATION
Abbreviation | Extended Form |
EG | Engineering |
SOP | Standard Operating Procedure |
QA | Quality Assurance |
NA | Not Applicable |
11.0 REVISION HISTORY OF CHANGE
Sr. No. | Date | Revision Details | Revision No. |