- OBJECTIVE
To lay down the procedure for operation of AHU.
- SCOPE
This SOP is applicable in Engineering for operation of AHU.
- RESPONSIBILITY
Supervisor / Executive : | : | To follow the procedure |
- ACCOUNTABILITY
Head Engineering : System Compliance
- PROCEDURE
- Operation: Pre Startup Checks:
- Ensure that the electrical supply is available for Air Handling Units.
- Ensure & Check chilled water is flowing through cooling coil by observing the pressure gauge located in the outlet line. Out let pressure shall be NLT 1.0 Kg/cm2.
- Ensure & Check Hot water flowing through Hot water heating coil by observing the pressure gauge located in the outlet line. Out let pressure shall be NLT 1.0 Kg/cm2.
- Hooter alarm shall be ON at the time of AUH ON & at the time of OFF it shall be OFF
- Switching ON the Air Handling
Unit:
- Switch ON the Air Handling Units by pressing the green button on the panel and red indicator should glow Check Motor bearings and lubricate the bearings.
- Air Handling Units shall run continuously until unless it is informed by concerned department.
- Sequence of Switching ON the Air Handling unit.
- When the AHU is in OFF condition, first switch ON the more pressurized area AHU, with respect to adjacent area AHU.
- Then switch ‘ON’ the less pressurized area AHU & continue the series according to the area pressure.
- When the AHU is in running condition, first switch OFF the less pressurized area AHU, with respect to adjacent area AHU.
- Ware House department Chemist / Officer shall be responsible for air handling unit ON OFF procedure for all sampling & dispensing area AHU.
- Operation: Pre Startup Checks:
Note: If Hooter alarm show, stop the AHU & check AHU for any abnormality
- Sequence of Switching OFF the Air Handling unit:
- Get the confirmation from concerned department for switching OFF the Air Handling Unit.
- AHU operation record shall be maintained by operator and verified by concern department.
- Check the Manometer reading for cleaning condition of filter. It should be between 5 – 20 mmHg. If it shows out of specification, clean the filter.
- Record the reading of manometer.
- Operate the AHU of core area on 24 Hour basis. Supervisor shall switch OFF AHU, after getting written information from user department.
- Engineering department shall inform to concern department for filter cleaning & Preventive maintenance of AHU.
6.0 TRAINING
Trainer : Head – Quality Assurance& Engineering Department.
Trainees : Engineering- Executive & Supervisors.
7.0 DISTRIBUTION
Master Copy : Quality Assurance Department
Controlled Copy : Engineering Department
Display Copy : Engineering Department (If Required)
8.0 ATTACHMENTS
Nil
- REFERENCES
In-house
10.0 ABBREVIATION
Abbreviation | Extended Form |
EG | Engineering |
SOP | Standard Operating Procedure |
QA | Quality Assurance |
WH | Warehouse |
NA | Not Applicable |
MB | Microbiology |
11.0 REVISION HISTORY OF CHANGE
Sr. No. | Date | Revision Details | Revision No. |
1 | 18/01/2020 | New SOP | 00 |