OBJECTIVE
To describe the procedure for cleaning of gelatin feeding pipe.
2.0 SCOPE
This SOP is applicable for procedure of cleaning of gelatin feeding pipe.
3.0 RESPONSIBILITY
Production Chemist & operator : To follow the procedure
4.0 ACCOUNTABILTY:
QA & Head Production : For system compliance
5.0 | PROCEDURE |
5.1 | Cleaning of gelatin feeding pipe: |
5.1.1 | Affix ‘TO BE CLEANED’ Status label from gelatin feeding pipe. |
5.1.2 | Take gelatin-feeding pipe in to the washing area. |
5.1.3 | Pass Hot water thoroughly inside of the gelatin-feeding pipe to remove residue. |
5.1.4 | Finally rinse with purified water. |
5.1.5 | Clean the out sides by soaking lint free cloth. |
5.1.6 | Keep the gelatin- feeding pipe for air dry |
5.1.7 | Intimate IPQA Executive for clearance of gelatin feeding pipe. |
5.1.8 | Affix the label “CLEANED” on Gelatin feeding pipe after getting clearance from IPQA Executive. |
6.0 TRAINING
Trainer : Head – Production Department
Trainees : Staff and machine operator of the gelatin section and QA chemist.
7.0 DISTRIBUTION
Master Copy : QA Department
Controlled Copy : Production Department
Display Copy : Production Department
8.0 ATTACHMENTS
Nil
- REFERENCES
In-house
10.0 ABBREVIATION
Abbreviation | Extended Form |
EG | Engineering |
SOP | Standard Operating Procedure |
QA | Quality Assurance |
WH | Warehouse |
NA | Not Applicable |
MB | Microbiology |
11.0 REVISION HISTORY OF CHANGE